Greg returns for this weeks renovation update and there is A LOT to cover!
The stage has been removed for fireproofing and will be reinstalled when that process is complete. When the renovation project concludes we will resume our main stage music with acts like The Machine, Miller Campbell, and more!
Cosmetic updates to the Sports Bar and the last portion of the gaming floor are still underway.
The mechanical ducting is being installed in this area as well. When that installation is complete and the walls around that area come down our new HVAC system will be fully online. You will notice a huge difference in air quality when you come visit us!
You can watch the renovation update for this week in its entirety below:
We thank you for your patience as we enter the home stretch. Stay tuned for more information about our grand reopening festivities coming soon!